Thursday, June 4, 2009

Affixing the Hardware

More good work today. Our electrician crew grew substantially, and they made good progress installing lighting. The plumbers delivered the water heaters, installed faucets, an In-sinkerator, and the dishwasher. The low voltage installer has pretty much finished up the speaker installation on the upper floors. The vanity tops were installed downstairs. The cement guys got forms in place but haven't poured the concrete yet. Hopefully tomorrow...